A1
Action A1: Administrative activities related to the project start.
START: 1/12/2012 - END: 30/06/2013 -
Action A1: Administrative activities related to the project start.
START: 1/12/2012 - END: 30/06/2013 -
Action A2: Creation of a coordination committee for the management and conservation of the river Po with particular regard to the Rete Natura 2000.
START: 1/12/2012 -- END: 30/06/2013
Action A3: Restoring works of the river corridor continuity, of the control system and other structural interventions planned.
START: 1/12/2012 - END: 31/12/2013 -
Action B1: Provision of land for the fish pass construction at Isola Serafini.
START: 1/07/2013-- END: 31/01/2018
Action C1: Construction of fish pass with attached control system at Isola Serafini.
START: 1/01/2014 - END: 31/12/2015